Lessons Learned and Benefit Realization:
The Project Portfolio Risk Management (PPRM) process does not end when the project solution(s) is/are implemented. The PPRM process includes steps to capture and share lessons learned and to measure and compare benefits realized from project. The sections below provide the high-level process flow and additional details on each of those steps.
Lessons Learned:
Lessons learned are captured throughout the project and shortly after project completion using a standard spreadsheet created and provided by the Large Project Delivery (LPD) team. The lessons learned spreadsheet contains data elements for each lesson learned that the LPD team has determined to be essential to drive consumption and value for future projects. The key data elements captured are:
- Project Name
- Focus Area (project area impacted most by the lesson learned)
- Description
- Recommendation
- Project Impact
The LPD team adds the lessons learned captured from each project into a consolidated lessons learned spreadsheet that is archived on the Microsoft SharePoint (MS SP) site and made available to future projects during the Enhanced Project Selection, Solutions, and Preparation phase of the PPRM process. In this manner, the PPRM process comes full circle with a 360° feedback loop.
Benefit Realization:
While on-time and on-budget project delivery is an important piece for project success, it is not the only success criteria for large-scale Information Technology (IT) projects. Success criteria is also measured by the benefits that the project brings to State of Indiana (SOI) employees and constituents.
Benefit measurements are taken at the appropriate timing post project completion (6 – 12 months typically). The results are compared with the expected benefits captured during the Enhanced Project Selection, Solutions, and Preparation phase of the PPRM process and the results of that comparison determine the level of project success from a benefits realization perspective.
Results are documented and included in the consolidated lessons learned spreadsheet to help guide benefit goal setting and measurement on future large-scale IT projects at the SOI.